Review of the Delivery of Major Road Infrastructure Projects
September 19, 2024
Arrière-plan
The commission included a review of the delivery of the Botley Road and Access to Headington projects and comprised:
- High level review of the Highway Partnership Contract (HPC) under which the Task Orders for the individual contracts were issued
- Review of programme and progress management
- A commercial account audit
- Review of the project management and compliance with the prevailing project governance process and guidelines
- Provision of a report on findings and any lessons to be learnt for future projects
Services fournis
Rimkus was commissioned to provide commercial consultancy services to Oxfordshire County Council in connection with the delivery of major road infrastructure projects. The commission was led up by a Rimkus director along with a team of senior consultants and quantity surveyors.