Ontario Building Safety Regulations at a Glance
|
Requirement |
Applies To |
Cycle |
Next Deadline |
Penalty |
|---|---|---|---|---|
|
O. Reg. 506/18 (EWRB) |
Privately owned buildings with 50,000 sq. ft. (4,645 m²) or larger |
Annual |
July 1 each year (2025 data: July 1, 2026) |
Fines under the Electricity Act, 1998; public disclosure of non-compliance |
|
OBC 3.2.7.9 — Emergency Power for Building Services |
Buildings over 36 m (approx. 118 ft.) measured from grade to floor level of top story |
Every 10 years |
10 years from previous inspection |
Code enforcement; occupancy implications |
|
Facade and Structural Inspections |
No provincial mandate for existing buildings |
No mandated cycle |
Voluntary best practice |
No provincial penalty; civil liability exposure if failure causes injury |
Sources
Ontario Building Safety Regulations: What Building Owners Need to Know
In the province of Ontario, Canada, there are two active regulatory requirements for certain buildings that meet the mandates’ thresholds.
Ontario Regulation 506/18: Reporting of Energy Consumption and Water Use
Under the Electricity Act, 1998, O. Reg. 506/18 (EWRB) requires the previous year’s energy and water usage of privately owned buildings, that are 50,000 sq. ft. (4,645 m²) or larger, be reported annually by July 1. Reports need to be submitted to the Ministry of Energy and Mines via ENERGY STAR Portfolio Manager.
The penalty of missing the deadline can include fines and public disclosure of non-compliance. Buildings 100,000 sq. ft. or larger also require third-party data verification in Year 1 and every five years thereafter. Publicly owned buildings, or buildings where more than 50% of the gross floor area is occupied by a public agency, are exempt from reporting.
Ontario Building Code, Article 3.2.7.9: Emergency Power for Building Services
Under the Ontario Building Code (2024 edition, in effect January 1, 2025), OBC 3.2.7.9 requires emergency power system inspections every 10 years for buildings over 36 m (approx. 118 ft.) in height, measured from grade to top story floor level. The OBC governs all new construction, but does not mandate ongoing inspection cycles for existing building envelopes. Instead, building owners bear the full responsibility of proactive maintenance.
The absence of a facade inspection mandate is a well-documented regulatory gap. The 2014 Elliot Lake Commission of Inquiry recommended periodic structural inspections for existing buildings, but as of 2025, this recommendation has not been enacted. In practice, well-managed buildings in Ontario conduct voluntary condition assessments on a five-year cycle, the same cadence used in mandated programmes in New York City and Quebec.
O. Reg. 506/18 (EWRB) and OBC 3.2.7.9 (OBC): What Applies to Your Building
Key Definitions Used
Building Height
- Measured from grade to the floor level of the top story, not the roof
- OBC threshold: more than 36 m (approx. 118 ft.)
Certified Professionals
EWRB data verification must be provided by a professional with one of the following credentials:
- Professional Engineer (P.Eng.)
- Building Energy Technology Certification
- Building Operator Certification
- Building Science Specialist of Ontario
- Certified Energy Auditor
- Certified Building Commissioning Professional
- Portfolio Manager certification
OBC inspections must be completed by a registered architect or licensed P.Eng.
Gross Floor Area (GFA)
- Total enclosed floor space measured between exterior wall surfaces, in sq. ft. or m²
- EWRB threshold: 50,000 sq. ft. (4,645 m²) or more, inclusive
Toronto Dual Reporting
- Buildings ≥ 50,000 sq. ft. in the City of Toronto must also report EWRB data under Municipal Code Chapter 367

Reporting Exemptions
- Buildings owned by a public agency, or where at least 50% of GFA is occupied by a public agency, are exempt from EWRB reporting
- One-year exemptions from EWRB reporting may be available if the property is newly constructed with a certificate of occupancy issued in the reporting year
- Submit an exemption request or learn more about exemption criteria at the Government of Ontario website
What to Submit via ENERGY STAR Portfolio Manager
O. Reg. 506/18 | EWRB
|
Data Category |
Required Fields |
|---|---|
|
Building identification and contact |
Building name, address, EWRB ID, owner/contact name and email |
|
Building characteristics |
Gross floor area in m² (Portfolio Manager uses metric), primary occupancy type, number of residential units if applicable |
|
Energy, water, and meter data |
Meter numbers and utility account IDs; annual electricity (kWh); annual natural gas/fuel consumption; annual water use (m³) |
|
Reporting period |
Full calendar year (January 1 to December 31). Common error: submitting partial-year data. Also include exemption documentation if applying. |
Emergency Power
OBC 3.2.7.9
Buildings over 36 m (approximately 118 ft.) measured from grade to the floor level of the top story must maintain emergency power systems capable of operating under full load for not less than 2 hours, and have them inspected every 10 years by a registered design professional in responsible charge. The 10-year inspection cadence is governed by the Ontario Fire Code (O. Reg. 213/07), not the OBC itself, which covers installation requirements only.
Required Emergency Power Systems
Per OBC 3.2.7.9, verified against official 2024 OBC Compendium, O. Reg. 163/24.
|
OBC Clause |
Required System |
Status |
Notes |
|---|---|---|---|
|
3.2.7.9.(1)(a) |
Every elevator serving stories above the first story in a building more than 36 m high, and every elevator for firefighters |
MANDATORY |
EPS not less than 2 h full load |
|
3.2.7.9.(1)(b) |
Equipment supplying water for fire suppression where supply depends solely on electrical power (see clause (4) for exemption) |
MANDATORY |
2 h full load |
|
3.2.7.9.(1)(c) |
Fans and other electrical equipment to maintain air quality per Articles 3.2.6.2. and 3.3.3.6. |
MANDATORY |
2 h full load |
|
3.2.7.9.(1)(d) |
Fans required for venting by Article 3.2.6.6. |
MANDATORY |
2 h full load |
|
3.2.7.9.(1)(e) |
Smoke control fans per Clause 3.2.8.4.(1)(c) and Article 3.2.8.7. in buildings within scope of Subsection 3.2.6. |
MANDATORY |
2 h full load |
|
3.2.7.9.(4) |
EXEMPTION: EPS for water supply under (1)(b) not required for NFPA 13D sprinkler systems (one- and two-family dwellings). |
EXEMPTION |
OBC 3.2.7.9.(4) |
Penalties and Consequences
O. Reg. 506/18: EWRB Non-compliance
- Failure to comply is an offence under s. 25.35.8 of the Electricity Act, 1998, with administrative penalties governed by O. Reg. 12/23
- Non-compliance data publicly disclosed by the Ministry of Energy and Mines
- Potential insurance implications: non-reporting properties may be considered higher risk by insurers at policy renewal
Facade and Structural Non-compliance
- No provincial fine for failing to inspect a facade, but civil liability exposure applies if failure results in injury or property damage
- Courts may consider whether owners acted on visible or reported signs of deterioration
- Insurance coverage for facade-related incidents may be affected where no maintenance records exist
Proactive Maintenance
Ontario has no facade inspection mandate, but the risk of undetected building envelope deterioration is real. Rimkus engineers conduct voluntary condition assessments and envelope performance evaluations across Ontario, helping building owners identify issues early and plan capital maintenance before problems become emergencies.
Other Regulatory Requirements for Buildings
- Ontario Fire Code (O. Reg. 213/07): fire safety plans, system testing and inspections, enforced by municipal fire departments. ontario.ca/laws/regulation/070213
- TSSA: elevators, boilers, and pressure equipment require registration and periodic inspections. tssa.org
- Electrical Safety Authority (ESA): electrical safety standards and contractor permit requirements. esasafe.com
- Condominium Act, 1998: reserve fund studies and board governance duties for condominium corporations. ontario.ca/laws/statute/98c19
How Rimkus Can Help
- Voluntary building envelope condition assessments and facade evaluations
- EWRB compliance support: energy audits and data verification for O. Reg. 506/18 reporting
- OBC 3.2.7.9 emergency power system inspections and documentation
- Restoration design services for deterioration identified during assessments
Frequently Asked Questions
Need Help? Contact Rimkus
Ontario’s EWRB and OBC 3.2.7.9 requirements are active and enforced. Rimkus’ licensed engineers and building science professionals perform inspections, assessments, and compliance support across Ontario, helping building owners stay ahead of their obligations and protect their assets.
Schedule a Consultation
- Phone: +1 905 607 7244
- Toll free: +1 888 607 5245
- Email: [email protected]
Office Address
2121 Argentia Road, 4th Floor
Mississauga, Ontario L5N 2X4, Canada
Meet Our Ontario Team
Additional Insights on Ontario Regulations
External Resources
- Ontario Regulation 506/18 | Reporting of Energy Consumption and Water Use (Official e-Laws)
- Ontario Building Code (2024) | Ontario Ministry of Municipal Affairs and Housing (Official)
- Guide to Energy and Water Reporting | Ontario Ministry of Energy and Mines (Official)
- Report Energy and Water Use for Large Buildings | Ontario.ca (Official)
- City of Toronto | Energy and Water Reporting for Buildings (Official)
- Ontario Fire Code (O. Reg. 213/07) | e-Laws (Official)
- TSSA | Technical Standards and Safety Authority (Official)
- Report of the Elliot Lake Commission of Inquiry (October 2014)